Project Status: Construction

City/Town: Langley

Project Scope: This project includes the seismic upgrade and 11 classroom addition at Peter Ewart Middle School. The project will add 275 student seats, creating a total of 900 safer seats at the school. There will be minimal impact on student learning during construction as the expansion will make use of repurposing underutilized space. 

Estimated Project Value: $38.8 million

News Release: Students at Peter Ewart Middle school to get safer, expanded school

School Website

Estimated Project Milestones

Tender and Award: Spring 2023
Construction Initiation: Summer 2023
Occupancy: Fall 2024