Project Status: Occupied
City/Town: New Westminster
Project Scope: This project includes a full seismic replacement to build a new Skwo:wech Elementary school, an immediate priority under the Province’s Seismic Mitigation Program. The new school will have three more classrooms to accommodate enrolment growth (80K/425E Capacity). There will be space for the existing StrongStart program within the school, and a Neighbourhood Learning Centre to accommodate the existing before- and after-school care programs, which are housed in a portable and an outbuilding. Students will stay in the current building while the new Skwo:wech Elementary school is being built.
Estimated Project Value: $34.98 million
News Release: New and improved schools on the way for New Westminster students
Tender and Award: January 2020
Construction Initiation: Summer 2021
Occupancy: Spring 2022
Dave Crowe
Manager, Projects & Capital Planning
Phone: 604-517-6288