Tree Farm Licence target release dates

Last updated on September 10, 2024

Please note these are estimated dates only and are subject to change. The schedule will be updated as information is available.

On this page

This site provides the schedule for each Tree Farm Licence (TFL) under the current round of Timber Supply Review.


Coast Tree Farm Licence (TFL) schedule

TFL Licensee Current AAC decision (determination date) Section 8 deadline Next AAC decision
(fiscal year*)
6 Western Forest Products Inc.** 10-Feb 12 10-Feb-2022 2020/21
19 Western Forest Products Inc. 10-Aug-10 10-Aug-2022 2018/19
25 Western Forest Products Inc 1-Feb-08 1-Feb-2018 2017/18
26 The Corporation of the District of Mission 7-Jul-20 7-Jul-30 2030/31
37 Western Forest Products Inc. 25-Jul-18 25-Jul-2028 2028/29
38 Northwest Squamish Forestry Limited Partnership 29-Aug-24 29-Aug-2034 2034/35
39 Western Forest Products Inc. 29-Aug-16 29-Aug-2026 2026/27
43 Kruger Products L.P. 31-Mar-21 31-Mar-31 2031/32
44 Tsawak-Qin Forestry Inc. 5-May-11 5-May-2021 2019/20
45 International Forest Products Ltd. 15-Jul-09 15-Jul-2019 2019/20
46 Teal Cedar Products Ltd. 28-May-24 28-May-2034 2034/35
47 TimberWest Forest Corp. 4-Feb-14 4-Feb-2024 2024/25
54 Ma–Mook Natural Resources Ltd. 7-Feb-19 7-Feb-2029 2029/30
58 A&A Trading (Haida Gwaii) 27-Oct-20 27-Oct-2030 2030/31
60 Taan Forest Limited 27-Oct-20 27-Oct-2030 2030/31
61 Pacheedaht Andersen Timber Holdings Limited Partnership 31-Oct-19 31-Oct-2029 2029/30

Northern Interior Tree Farm Licence (TFL) schedule

TFL Licensee Current AAC decision (determination date) Section 8 deadline Next AAC decision
(fiscal year*)
1 Coast Tsimshian Resources Limited Partnership 20-Jul-2021 20-Jul-2031 2031/32
30 Canadian Forest Products Ltd. 6-Feb-14 6-Feb-2024 2024/25
41 Skeena Sawmills Ltd. 10-Sep-2024 10-Sep-2034 2034/35
48 Canadian Forest Products Ltd. 15-Oct-15 15-Oct-2025 2025/26
53 Dunkley Lumber Ltd. 12-Apr-2022 12-Apr-2032 2032/33

Southern Interior Tree Farm Licence (TFL) schedule

TFL Licensee Current AAC decision (determination date) Section 8 deadline Next AAC decision
(fiscal year*)
3 International  Forest Products Ltd. (Interfor) 18-Jul-2024 18-Jul-2034 2034/35
8 Interfor Corporation 10-Feb-22 10-Feb-32 2032/33
14 Canadian Forest Products Ltd. 18-Apr-19 18-Apr-2029 2029/30
18 Canadian Forest Products Ltd. 13-Jul-2017 13-Jul-2027 2027/28
23 International Forest Products Limited 18-Jul-2024 18-Jul-2034 2034/35
33 Federated Cooperatives Limited 14-Dec-2021 14-Dec-2031 2031/32
35 West Fraser Mills Ltd. 1-Mar-12 1-Mar-2022 2021/22
49 Tolko Industries Ltd. 24-Feb-12 24-Feb-2022 2021/22
52 West Fraser Mills Ltd. 17-Jun-19 17-Jun-2029 2029/30
55 Louisiana – Pacific Canada Ltd. 24-Mar-17 24-Mar-2027 2027/28
56 Revelstoke Community Forest Corporation 4-May-21 4-May-2031 2031/32
59 Weyerhaeuser Company Ltd. 14-Mar-19 14-Mar-2029 2029/30

* Fiscal Year is April 1 to March 31.