Open. Construction underway. A historic slide reawakened in 2020 causing ground movement affecting Highway 97.
Construction Update – August 2024
Construction on the Highway 97 at Cottonwood Hill Project is underway. Drivers will see work on 1.4 km of Highway 97, including realignment of approximately 500 metres of road through the slide area and removal of weight from the top of the slide to improve safety and road stability. During construction, single-lane traffic will be implemented in both directions at times, and later this summer there may be single-lane alternating traffic with stoppages of up to 20 minutes.
In addition, tree clearing work is underway in Dragon Lake Quarry, which is expected to take approximately a month.
Please drive with caution through the construction zone.
Highway 97 at Cottonwood Hill is located approximately 18 km north of Quesnel.
Highway 97 at Cottonwood Hill is currently open. The Cottonwood Hill project includes stabilization of the affected area of Highway 97, a north-south route that provides access to communities in the region and is vital to B.C.’s economy.
The project team undertook work to determine a safe and climate resilient solution, which included:
The project will be completed in three phases, with the first phase complete.
Notification of project-related fieldwork or construction is posted on this page in advance. For the latest information on road conditions, please visit DriveBC.
Construction of phase 2, Highway 97 realignment and crest unloading, started mid-July 2024 and is scheduled to take one year. The subsequent phase of construction, which includes improving slope stability in the slide area, is scheduled to start in 2025.
An information session was held in Quesnel on November 9, 2023 regarding the Highway 97 at Cottonwood Hill project.
You can share your feedback with the project manager. Use the subscribe feature to be informed of opportunities for public engagement and updates to this page.
Progress updates
September/October 2023
Ministry contractors installed groynes along the Cottonwood River adjacent to the highway. Built with large rock material, groynes redirect river flows away from the slide area. Photos can be viewed in the photo gallery.
August/September 2023
An access road to construct groynes was built.
March 2022
An online engagement period was held to introduce the Cariboo Road Recovery Projects to the public and gather feedback.
February 2022
Door-to-door visits to nearby residences to inform community members of the project and potential options being considered. Residents were able to provide feedback on the projects and considerations for the project team.
November 2021
An in-person drop-in session at Kersley Hall was held to provide updates on the Highway 97 at Cottonwood Hill Project.
Fall 2021
Temporary road resurfacing was completed on Highway 97 at Cottonwood Hill to improve rideability for road users.
2020/2021
A slide in 2020 caused ground movement, impacting use of Highway 97 at Cottonwood Hill.
News
Notifications
March 2024
As a part of ongoing project planning and site preparation, crews are scheduled to be on site in March for tree clearing. Some of this work will take place near Highway 97 and may require temporary lane closures, so drivers are asked to use caution and observe signage when passing through the project area.
September 2023
Starting the week of September 4, 2023, for approximately one month, Ministry of Transportation and Infrastructure contractors are scheduled to install groynes along the Cottonwood River adjacent to Highway 97. This work is part of Phase 1 of the Highway 97 at Cottonwood Hill project. An intermittent closure of the northbound right lane of Highway 97 is anticipated to be in place during this time. More information.
Enter your email address to subscribe to updates of this page.