The ministry expects the following communication should occur when a source parcel responsible person is applying for an Approval in Principle or Certificate for the source parcel and for one or more affected parcels.
The requirements do not replace the conditions for public consultations under Section 52 of the Environmental Management Act (EMA).
The responsible person for the source parcel must provide a fully completed Notice of Likely or Actual Migration (NOM) (Online Form) to the affected parcel owner and the ministry as required under Sections 57 and 60.1 of the Contaminated Sites Regulation (CSR).
Once a NOM is sent, the responsible person for the source parcel should send a registered letter to each affected parcel owner with the following information:
The information on this web page does not replace the legislative requirements in the EMA or its regulations and it does not list all provisions for contaminated site services.
If there are differences between this information and the Act, Regulation, or Protocols, the Act, Regulation, and Protocols apply.