Nicomen River Bridge

Last updated on November 8, 2024

Nicomen River Bridge

Nicomen River Bridge is located 19 km south of Spences Bridge.

Overview of the project

  • Replace damaged Highway 1 Nicomen River Bridge
  • Armor embankment
  • Rehabilitate pavement on bridge approaches

Status

  • Highway bridge now open to 2 lanes
  • Temporary single lane bridge removed
  • Planting, hydroseeding and other site activities ongoing
  • Work is expected to be completed onsite in December 2024
  • Warranty inspections and defect corrections will continue through 2025 and 2026

Traffic impacts

  • Reduced speed limits
  • Intermittent single lane alternating traffic
  • Anticipated delays: 15 minutes
  • Check DriveBC.ca for current conditions

Project benefits

  • Improved safety and reliability
  • Improve climate resiliency
  • Opportunity for local communities and businesses

Project videos

 

Highway 1 – Nicomen River Bridge

Timelapse video of sliding the temporary bridge into place.

Photo gallery

Connect with TranBC

Visit the TranBC blog

Contact information

Friendly Url for this Page:
gov.bc.ca/NicomenRiver

For information about this project, contact

Lindsey LeBlanc
Project Manager