Highway 1 - Chase East (Chase West to Chase Creek Bridge)

Last updated on September 20, 2024

The Highway 1 Chase East Project will improve safety and access for vehicles and active transportation along Highway 1 through the Village of Chase.

The Highway 1 Chase East Project will improve safety and access for vehicles and active transportation along Highway 1 through the Village of Chase.

Please watch for project-related traffic pattern changes within the Village of Chase. Be patient, comply with traffic control and follow the signs.

What to expect

Travellers

Residents

  • Until November 2024, project construction make take place on Sundays. This change is in place to make up for lost time as a result of 2024 wildfire season restrictions. Residents near the project may experience increased noise levels
  • Expect noise from construction activities (the needs of local residents and the travelling public are considered when scheduling disruptive work)
  • Expect additional construction vehicles and equipment in the area

Project overview

  • Widen 1.6 km section of Highway 1 to four lanes and incorporate median and roadside barriers
  • Create a new, grade-separated interchange at Brooke Drive
  • Install two grade-separated pedestrian paths over Highway 1 with connections to Scatchard Trail
  • Provide municipal infrastructure improvements, including traffic and pedestrian safety enhancements along Brooke Drive to Shuswap Avenue

Status

  • Construction
    • On site Prime Contractor: CIF Construction LTD
    • Current focus: Ground stabilization work for the new overpass
  • Anticipated project completion: fall 2025
  • Read monthly updates

Project map

Chase West to Chase Creek Bridge Project

Technical documents

Project concept

Chase West to Chase Creek Bridge Drone Footage (May 2020)”


Chase Drive Through Brooke Drive 2021

 

Contact information

For more information about the Chase Four Laning highway project, contact

Chase East Contractor, CIF Construction Ltd.
Scott Fomenoff

Project Manager
Greg Jones

 

Chase East Contractor, CIF Construction Ltd. Phone
778‐835‐5357
Chase East Contractor, CIF Construction Ltd.
scott.fomenoff@cifcon.com