A release notice is not the same as a certification document.
On this page
Situations that qualify for a release notice
Scenario 1: Site investigation is not required before municipal or subdivision approval
This option applies when approval is required to prepare a site for redevelopment, such as:
- When zoning approval is required to secure funding from a lender
- Subdivision for municipal road dedications
- A site owner wants to complete upgrades to a site with ongoing Schedule 2 uses
This is not an exhaustive list. There may be other situations when site investigation is not required before approval.
Scenario 2: No significant threat or risk if municipal or subdivision application is approved
This option is for limited situations when a site doesn't qualify for the other types of release notices or a certification document, and there would not be a significant threat or risk if the municipal or subdivision application were approved.
Scenario 3: Remediation is part of site redevelopment
This option applies when you plan to remediate a contaminated site during redevelopment. In most cases, you must complete remediation within 5 years after the issue date of the release notice.
Apply for a release notice
1. Before applying for a release notice, make sure you've:
2. Complete a Contaminated Sites Services Application.
3. Prepare a letter signed by the owner or operator that outlines:
- The site ID number
- The site address and parcel identifier (either PID(s) for private land, or PIN(s) for provincial Crown Land)
- Identification of the owner or operator
- Identification of the agent acting on behalf of the owner or operator (if there is one)
- The municipal applications associated with the release request, including permit application numbers and dates
Include supporting documents and information depending on the scenario you are applying for:
Scenario 1: If site investigation is not required before municipal or subdivision approval
Include in your letter:
- Reasons why you qualify for this scenario
- A brief description of the site history and current use
- A description of the proposed activity
- Confirmation that additional approvals list in section 40 of EMA will be required if the site is redeveloped in the future
Include a map of the site:
- For site upgrades, the map should show the proposed work area
- For subdivision, the map should show the proposed subdivision plan and clearly detail where Schedule 2 uses occurred
Scenario 2: No significant threat or risk
Provide sufficient supporting information that clearly demonstrates that there would not be a significant threat or risk if the municipal or subdivision application were approved. Include the following information:
Additional supporting information may include, but is not limited to:
- Details about the use of intrinsic or engineered risk controls,
- Performance verification plans
Scenario 3: If remediation is part of site redevelopment
Include the following items:
- Site investigation reports as required by section 6.2 of the CSR, including a preliminary site investigation (PSI) and, if contamination is found, a detailed site investigation (DSI)
- A completed Site Risk Classification Report
- A site remediation plan and a schedule for completion of remediation
- Pre-approvals or approvals under protocols (if required) obtained before applying for a release notice
- A signed statement from an approved professional that confirms:
- They've reviewed applicable protocols and guidance and available site information
- All contamination at and migrating from the site has been delineated onsite and on neighbouring parcels
- Remediation of the entire extent of contamination at the site to applicable standards is achievable before completion of a final building inspection or issuance of an occupancy permit
- Following remediation, the site will be eligible for a Certificate of Compliance
- A commitment letter signed by the site owner or operator that confirms:
- The parcel will be remediated in accordance with the remediation plan
- Remediation will be completed before the endpoint specified by the approved professional
For this scenario, remediation must be completed within 5 years from the issuance of a release notice. You will be required to submit:
The ministry tracks these reporting requirements. This information is available on the Site Registry. Read more: Section 54(3)(d) of the Environmental Management Act
3. Submit completed documents and information to SiteID@gov.bc.ca
4. Pay ministry fees. The ministry charges fees for processing and reviewing release notice applications.
Alternatives to a release notice
Release notices do not eliminate future site identification and disclosure requirements. In some cases, certification documents may be preferred because:
- They remove restrictions on current and future municipal and subdivision approvals
- They can be useful to secure financing from a lender, to demonstrate due diligence or to facilitate property sales