The Capital Asset Management Framework is based in part on the principle of strong accountability in a flexible, streamlined process. Agencies are free to carry out their capital mandates with minimum intervention from the Province with flexible guidelines to encourage innovation and to accommodate differences in agencies, projects and the factors driving service delivery needs. At the same time, agencies must be fully accountable for managing capital assets effectively.
Reporting and monitoring are essential to accountability as well as to effective risk and cost management. The Budget Transparency and Accountability Act requires public agencies to publish financial and other information on capital projects with provincial contributions over $50 million.
Agencies need to gather and report relevant information about a project’s status such as the physical progress, financial information, risk assessment and any other elements necessary to understand the status of the project to appropriate stakeholders in a timely manner to support informed
decision making. Additionally, strategies to effectively manage variations from the project’s approved plan should also be identified. Further information on reporting components provided in Table 10.2.
The following chapter supports these objectives by:
Public-sector agencies are required to report on the progress of capital projects and should develop processes to ensure that this occurs on a regular, timely basis.
Table 10.2. describes the standard reporting components that should be addressed, consistent with the parameters identified in the planning process, as part of the due diligence undertaken in reviewing service delivery options and developing business cases. These reporting components are relevant for both internal (agency) and external audiences.
Component | Description |
---|---|
Scope | A succinct but comprehensive description of the project’s approved scope, consistent with the scope established in the business case. Details of the project’s critical objectives should be provided along with the intended outcome such as a description of the end product or output including quality standards, tasks performed, resources consumed. Identifying the outcomes are important to measure the success of the project. |
Schedule | Agencies should provide itemized information regarding the project's schedule, with key milestone dates and corresponding project deliverables. |
Financial | Agencies should provide a breakdown of all the financial parameters for planning, design, construction, acquisitions and operation of the asset or service, including any revenue forecasts. This should include the cost to complete the project and identify any variances (with an explanation) from the original estimates. |
Other Critical Business Case Elements | Where relevant, agencies should provide information on any issues unique to the project’s business case, such as environmental assessments, alternative procurement methods, labour, legal and/or First Nations issues, or performance criteria. |
Agencies should develop internal policies and procedures to ensure there is routine, timely and relevant reporting of risk-related information to the appropriate decision- making authorities. This supports ongoing public accountability. It also supports agencies to meet requirements for various capital-related approvals.
Specifically, agencies should:
The Ministry of Finance is required to prepare regular public reports on the Province's economic and fiscal performance. Specifically, it must provide "planned versus actual" information on an aggregated agency basis (consolidating information from all public agencies that are part of a given reporting entity), and for specific projects where required by legislation or by Treasury Board.
As part of this process, agencies may be required (as communicated through a Crown agency mandate letter or Treasury Board Decision Letter) to provide monthly or quarterly reports to the ministry.
As part of this routine reporting, agencies are also required to report any material variations from a project’s approved parameters, including scope, schedule and cost and to identify strategies to effectively manage those variations. This variance-based approach to reporting has two important benefits:
Agencies may be required to submit a calendarized forecast of their overall capital expenditures at the beginning of the fiscal year and a Monthly Aggregate Report thereafter.
Generally, the calendarized forecast should be submitted within 15 working days of the start of the fiscal year. Monthly aggregate reports should be prepared on an accrual basis and submitted within 10 working days of the end of each month.
Figure 10.4.1 below provides an overview of the content of a typical monthly aggregate report.
Monthly Aggregate Report
Generally, the report includes:
In the event of a material variance between the actual monthly capital expenditures and the calendarized forecast capital expenditures, a variance report should provide the reason(s) for the variance.
In the event of a significant variance between an agency's total annual calendarized capital expenditures and its Capital Expenditure Limit, the variance report should provide:
For specific projects (generally those where the provincial contribution exceeds $50 million), agencies may be required to submit a calendarized forecast of capital expenditures at the beginning of the fiscal year and quarterly thereafter.
As outlined below in Figure 10.4.2, quarterly reports provide more detailed information than monthly aggregate reports. They should be prepared on an accrual basis and submitted to central government within 15 working days of the end of each fiscal quarter.
Figure 10.4.2
Quarterly Reports
Should include the following information:
Risk-based reporting is another component of the Province’s commitment to balance accountability with agency-level flexibility. Depending on the specific risk profile presented by a project and/or its sponsoring agency, the agency may be required to:
These requirements may be part of Treasury Board’s conditions for approval, or they may be outlined in an agency's Mandate Letter. See Figure 3.2.1, Project Risk Factors For examples of the factors considered by Treasury Board to determine the levels of oversight for capital projects.)
The overviews below indicate the levels of information appropriate for risk-based reporting on initiatives of different scope and complexity. Although the report components are identical, the level of detail required for each varies according to the project’s specific features.
Comprehensive Report
A comprehensive report would generally be used for high-risk, high-cost and/or high-profile initiatives. It would typically include:
Detailed Report
A detailed report would generally be used for moderate-risk, cost and/or profile initiatives. It would typically include:
Each time an agency reports to central government whether to meet public reporting requirements or Treasury Board risk-based oversight conditions, the report must be accompanied by correspondence signed by the responsible officer(s) attesting to the accuracy and completeness of the information provided.
Treasury Board or its designate may direct an independent third party to conduct audits or reviews to verify compliance with any reporting component, including any specific conditions of project approval. In exceptional circumstances or in high risk, complex projects, Treasury Board may also require independent, third-party oversight to monitor and report on a project’s progress.
9. Budget & Cost Management < Previous | Next > 11. Performance Measurement