Submission for Tenders Expires: July 23, 2024
Project Number: 13254-0003
Contract ID: 13254MJ0003
Location: The Site is located on Highway 1, Segment 0520, km 17.94 to km 18.22 on King Road and Riverside Road parallel to Highway.
Description: Relocate a short section of King Road tying into Riverside Road, south of Highway 1 for the future widening of Highway 1. Work includes but is not limited to the following: Traffic Management, Quality Management, Protection of the Environment, Survey and layout, Clearing and Grubbing, Roadway and Drainage Excavation, Construction of access roads, Removal of existing works, Municipal Utility Installation, Milling and Pavement Markings.
Document |
Document Description |
---|---|
1 |
|
2 |
|
3 |
|
4 |
|
5 |
Highway 1 P7 – King Road Realignment 100% Detailed Design Geotechnical Report – 2024-05-16 |
6 |
|
7 |
|
8 |
|
9 | 2300 Tender Data |
10 | FVH1CIP PLA Signed with Associated Letters |
11 | Letter for FVH1CIP Additional Scope of Work |
12 | Wage Grid May 2024 |