Submission for Tenders Expires: April 17, 2025
Project Number: 37721-0000
Contract ID: 37721MJ0000
Location: Adjacent to and below Highway 97, segment 1200, between LKI ~km 52.67 Big Bam Road and ~km 53.83 Taylor Bridge N abutment. Site 1 is approx 20m W of bridge, 70m N of riverbank. Site 2 is approx 50m W of S bridge embankment, 130m S of riverbank.
Description: Construction of two 1.5m diameter drilled shaft Osterberg Cell static piles with pile and cell testing
Document |
Document Description |
---|---|
1 |
|
2A |
|
2B |
|
2C |
|
3 |
|
4 |
|
5 |
|
6 |
|
7 |
Groundwater Testing Results and Safe Work Recommendations
|